After acceptance testing, what type of drawings are required to be presented to the building owner?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Study for the NICET Level 2 Fire Alarm Systems Test. Use multiple-choice questions with hints and explanations. Be fully prepared for your exam with detailed insights and resources. Get ready to succeed!

The correct answer is As Built Drawings. After acceptance testing of a fire alarm system, it is essential to provide the building owner with As Built Drawings. These drawings accurately reflect the final installed configuration of the system, detailing any changes made from the original design during the installation process. They serve as a vital reference for future maintenance and potential upgrades, ensuring that the owner has an accurate representation of what was actually installed.

In contrast, Contract Drawings typically represent the initial proposal before any modifications or installations are made, which may not correspond to the final product. Point-To-Point Diagrams offer details about the connections and pathways for the system's components but do not provide an overall layout. Manufacturer's Drawings highlight the specifications and designs provided by the equipment manufacturers, but they are not tailored to the specific installation and changes made on site. Thus, As Built Drawings are the most relevant and necessary documentation provided to the building owner after the acceptance testing is completed.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy